Data Center Cleaning

Date: October 2020

Tanziif was contracted to do a detailed deep cleaning for the Data Center at a soon to be commissioned HQ for a major airline in the UAE measuring 144365 sq.ft. Tanziif executed the scope of work which needed the cleaning in accordance with ISO 14644 Class 8 standards using ISO 140001 certified cleaning chemicals. The entire cleaning and assessment was scheduled for 10 working days but the Tanziif team managed to complete this within 7 days using equipment in accordance with IEC60312 international standards. The job was verified with a laboratory testing & report of conformity test in accordance with ISO 14644 Class 8 standards for the data hall.